The Section 278 Creswell Grove scheme is progressing well and is approaching completion of the present phase of works, which is to provide a new traffic lane on Creswell Grove to the west of the M6 J14.
The final resurfacing works require overnight closures both ways of A5013 Creswell Grove from 19th to 23rd October 2026. The 230m long full road closure, west side of M6 J14, will be implemented at 10pm on Monday 19th October until 6am on Tuesday 20th October. The A5013 will then reopen for eastbound traffic only during the day. The night-time road closures are then repeated over the nights of 20th – 23rd, until 6am on Saturday 24th October. Night-time works are preferred as it significantly reduces disruption to local businesses, residents and daytime road users and well reducing safety risks in relation to traffic leaving the M6 northbound at Junction 14. Access to individual properties will be agreed by the site team, emergency vehicles will continue to have access as required.
Completing these resurfacing works overnight in October will enable the current one-way road closure to be fully removed and the A5013 Creswell Grove to reopen both ways. This is planned for weekend of 31st October/1st November 2026. Following this phase, works will continue to the east of Junction 14 to deliver a new pedestrian refuge and undertake some resurfacing works on the roundabout.
S278 Highway improvement works associated with the ‘Stafford Gate’ commercial development are being undertaken on A5013 Creswell Grove, A5013 Eccleshall Road and M6 Junction 14, Stafford.
These works are being delivered by Alto Construct and funded by the developer, Strawsons Holding Limited
The scheme includes;
The Works commenced on 5th May 2026 for approximately 39 weeks
The works on A5013 Creswell Grove are expected to complete in November 2026.
The works on A5013 Eccleshall Road are expected to commence following the completion of works on A5013 Creswell Grove and are expected to complete by the end of January 2027.
The Contractor installed advance warning signs ahead of the works commencing. Any individual access concerns will be managed by the site teams.
The diversion routes during periods of one-way closure are shown on the following plans;
The final resurfacing works require overnight closures both ways of A5013 Creswell Grove.
To allow the works to be carried out safely, temporary traffic management will be required for the works duration.
This could alter as the scheme progresses. However, the expected phasing is as follows;
Site establishment and off-line works – 5th May 2026 for 2 weeks
No traffic management in place
Due to complete November 2026
18th November 2026 for approx. 4 weeks
Approximately 3 weeks
11th January 2027 for approximately 3 weeks - primarily night works
Please note that the safety of both the road users and the site workforce is paramount. Any road users who fail to comply with the traffic management measures in place will be reported to the Police. With any major road scheme, there will unfortunately be significant disruption, so we would like to thank people for their patience and understanding during the works period.