The S278 Creswell Grove scheme is now entering the final stages. Following the removal of the one way closure on Creswell Grove in late October, works now move to constructing a new pedestrian refuge on the A5013 Eccleshall Road, the east/town centre side of the M6. The new refuge and associated footway works, which is part of the scheme planning conditions, will improve pedestrian safety in the area.
The installation of the new refuge will require temporary traffic signals on the Eccleshall Road between 2nd Nov to 14th Nov.
The final works are on the M6 J14 roundabout to improve kerbing and renew carriageway surfacing, commence on the 22nd Nov, with resurfacing planned overnight on the 25th and 26th November, completing the scheme. Signed diversions via the A34 will be in place for the 25th and 26th overnight partial closures of the M6 J14 roundabout.
S278 Highway improvement works associated with the ‘Stafford Gate’ commercial development are being undertaken on A5013 Creswell Grove, A5013 Eccleshall Road and M6 Junction 14, Stafford.
These works are being delivered by Alto Construct and funded by the developer, Strawsons Holding Limited
The scheme includes;
The Works commenced on 5th May 2026 for approximately 39 weeks
The works on A5013 Creswell Grove are expected to complete in November 2026.
The works on A5013 Eccleshall Road are expected to commence following the completion of works on A5013 Creswell Grove and are expected to complete by the end of January 2027.
The Contractor installed advance warning signs ahead of the works commencing. Any individual access concerns will be managed by the site teams.
The diversion routes during periods of one-way closure are shown on the following plans;
The final resurfacing works require overnight closures both ways of A5013 Creswell Grove.
To allow the works to be carried out safely, temporary traffic management will be required for the works duration.
This could alter as the scheme progresses. However, the expected phasing is as follows;
Due to complete November 2026
18th November 2026 for approx. 4 weeks
Approximately 3 weeks
11th January 2027 for approximately 3 weeks - primarily night works
Please note that the safety of both the road users and the site workforce is paramount. Any road users who fail to comply with the traffic management measures in place will be reported to the Police. With any major road scheme, there will unfortunately be significant disruption, so we would like to thank people for their patience and understanding during the works period.