We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work, please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

A34 Highway Improvements, Stafford. Town Centre to Weeping Cross

funded-by-uk-government

What are we doing?

We will be carrying out maintenance and infrastructure improvements along the A34 Corridor, from Weeping Cross to the Town Centre.   

The scheme includes road and transport improvements including road and bridge maintenance work, active travel, passenger transport and street lighting improvements on the A34, between Stafford Town Centre and the A34/A513 double traffic island junction at Weeping Cross.    

Roads affected include A34 Lichfield Road, North Walls, Queensville Roundabout, Queensville, Radford Bank, Baswich Lane, Cannock Road and Weeping Cross.   

The roadworks are planned to be carried out in eight phases. Works started in early June 2024 and are planned to be completed March 2026.  Bus services will be affected between Queensville Roundabout and the Town Centre.  

You can find frequently asked questions here. If you have any questions, please email luf.stafford@staffordshire.gov.uk   

Upcoming traffic management measures  

6 November – 10 November 2025 

Dates: Thursday 6 November – Monday 10 November 2025 
Time of works: Off-peak hours, 09:30 – 15:30 daily 
Traffic control: Temporary traffic signals 
Note: Only one set of temporary signals will be in use at any given time 

Lichfield Road (between Queensville Avenue and Queensville Roundabout) 

Works include:  

  • Footway resurfacing 

  • Carriageway patching 

  • Guardrail/fencing installation 

Radford Bank, Stafford 

Drainage works at two locations:  

  • Site 1: Adjacent to BMW lookers garage 

  • Site 2: Between No. 17–25 Radford Bank 

Phasing of the Works

This page will be updated as information changes and further detail will be added when this becomes available.

This is the phasing plan:

Key:

Phases that are currently in progress
Phases that will start shortly
Phases that have been completed

 

Phase 1 - Gaol Square (Completed September 2024)

Phase 2 - Weeping Cross Roundabout (Completed October 2024)

Phase 2a - Queensville Bridge - Below Deck (Completed October 2024)

Phase 3 - Radford Bank - Queensville Roundabout (Completed May 2025)

Radford Bank Bridge (Completed July 2025)

Phase 4 - Queensville Roundabout (Completed June 2025)

Further detail: Queensville Roundabout plan

Phase 4a - Queensville Stores – Queensville Bridge  (Completed June 2025)


Phase 5 - Queensville Bridge – Above Deck (SCC Funded)  Construction 30/06/25 – 31/10/25*  

  • Carriageway and footway resurfacing over railway bridge
  • Waterproofing and footway protection to Railway Bridge
  • Partial segregated cycle route
  • Shared cycle route over Railway Bridge
  • *Works to parapet will be completed once railway possessions have been secured

Works are planned to be carried out under a one-way closure and diversion between Riverway and Queensville Roundabout. The direction of flow will be out of town. The local diversion route will be Silkmore Lane, Rickerscote Road and A449 Rising Brook and Wolverhampton Road.

Further detail: Bridge Section GA TM Diversion Route TM One way

Phase 5a - Queensville Stores - Queensville Avenue
Construction 30/06/25 – 21/10/25

  • Drainage Repairs and Improvements
  • Replacing worn out carriageway for approximately 120m from Queensville Stores
  • Carriageway patching
  • Refer to Phase 5 for works to Queensville Bridge – Above deck

Works are planned to be carried out under a one-way closure and diversion between Riverway and Queensville Roundabout.

The direction of flow will be out of town. The local diversion route will be Silkmore Lane, Rickerscote Road and A449 Rising Brook and Wolverhampton Road.

There will also be

  • Single lane entry onto Queensville Roundabout from A34 Queensville, Ampleforth Drive, Silkmore Lane and Queens Retail Park.
  • Temporary 3 way traffic control at Riverway / Lichfield Road junction, temporary pedestrian crossings, 20mph temporary speed limit and no right turn on adjoining side roads
  • Temporary footway closures and diversions

Dependent upon the activities there may be a need to close St Leonards and Queensville Avenue with its junction with A34 Lichfield Road from time to time. 
Final surfacing will be carried out under night-time closures between 8pm - 6am from 28 August 2025 until 10 October 2025 

Further detail: Phase 5 - GA TM One way TM Diversion Route 

Phase 6 - Queensville Avenue - RiverwayConstruction 30/06/25 – 24/10/25

  • Drainage Repairs and Improvements
  • Carriageway and Footway Resurfacing (SCC Funded)
  • Improved Pedestrian Crossing Points
  • Existing Traffic Signal Upgrade
    • Riverway Junction 30/06/25 – 18/07/25
    • Ranshaw Drive Junction 21/07/25 – 08/08/25
    • St Leonards Junction 11/08/25 – 22/08/25

These works will be carried out with a combination of one-way road closures and diversion, temporary pedestrian crossings, footway closures and diversions together with night time closures for surfacing as for Phase 5 and 5a.

Further detail: Phase 6 - GA  TM One way TM Diversion Route 

Queensville - Riverway Nighttime Surfacing Works ( 227 KB)

Riverway - Queensville Surfacing Works (591 KB)

Phase 6a – A34 Lichfield Road and its junction with Ranshaw Drive Completed May 2025 

Further detail: 

GA Ph 6a


Phase 7a - Bridge Street - Lichfield Road (Gyratory)
Construction 06/01/26 - 13/02/26

  • Pedestrian and cycle crossing / lane Improvement 
  • Right turn lane into Bridge Street at Newport Road junction 

For the traffic signal upgrade works temporary traffic signals will be in operation in lieu of permanent signals with footway works carried out with lane closures.
Resurfacing & lining works at Newport Road / Bridge Street junction will be carried out under nighttime closure, dates to be confirmed. 

Further details will be released in due course 

Phase 7b - Bridge Street - Lichfield Road (Gyratory) Construction 06/01/26 – 13/02/26 

Advance works 16/06/25 – 30/06/25 for this phase.  

  • Upgraded Pedestrian and Cycle Crossing
  • Bus Priority Measures between St. Leonard's Avenue & Bridge Street
  • Further details will be released in due course
  • Contra flow cycle lane along White Lion Street
  • Existing parking bays are to remain 

For the traffic signal upgrade works temporary traffic signals will be in operation in lieu of permanent signals with footway works carried out with lane closures.
Further details will be released in due course

Phase 8 - North Walls (Gaolgate Street - South Walls) (Completed April 2025)

 