Buildings and land

These pages will aim to provide you with information about the services on offer for your school property needs.

Assessment Management Plans (AMPs)

The Department for Education has determined the format and method for AMPs. All local authorities must maintain an AMP, and the DfE uses this to inform capital investment for each Local Authority.

Assessment

The assessment covers three core areas:

Asset Management Plan (AMP) Documents

Schools should use these documents to report AMP data changes to the Supplementary Planning Document (SPD), identify their highest priorities and preparing a 3 year AMP.

Condition Assessment

  • Roofs
  • Windows
  • Walls
  • Floors
  • Ceilings
  • Stairs
  • Sanitary services
  • Mechanical services (including heating systems)
  • Electrical services

How often

Specialist Surveyors from the Maintenance Consultancy undertake surveys within a 4-yearly cycle.

Grading

Each element is graded according to two criteria: its estimated life remaining and condition. 

Condition Definitions

Priority Definitions

  • Priority 1 -  Urgent work that will prevent immediate closure of premises and/or address an immediate high risk to the health and safety of occupants and/or remedy a serious breach of legislation.
  • Priority 2 -  Essential work required within two years that will prevent serious deterioration of the fabric or services and/or address a medium risk to the health and safety of occupants and/or remedy a less serious breach of legislation.

Determining Priorities

The AMP informs all aspects of planned capital investment.  In particular, issues included in the Authority's Planned Replacement Programme (PRP) use condition information in the AMP Database to prioritise. The authority consulted on changes to this PRP prioritisation method early in 2006, with the changes adopted from 2007/8.  The consultation paper can be found at Schools Capital Consultation.

The process is also explained in more detail in Staffordshire's revised AMP Statement of Priorities.