CX053 - Carriageway reconstruction works on the A513 Lichfield Road, Kings Bromley
We will be carrying out works along the A515 Lichfield Road, (from Cherry Lodge to the junction of the A513 Alrewas Road) and a section of carriageway surfacing at the junction of Crawley Lane.
Works will include the replacement and adjustments of kerbs where necessary, tactile crossing replacement, along with the removal of the existing carriageway ironworks and re-setting them. Following the above works, we will then begin the carriageway reconstruction works, this will include the removal of the existing carriageway surface and replacing it with a new surface, along with the replacement of new road markings.
Beginning on Monday 20 October 2025, we’ll begin the first phase of the scheme, where we’ll start the civil works.
These initial works will be carried out under temporary traffic signals during the daytime between the hours of 7.30am and 7.00pm. Temporary traffic signals may need to remain in place over night to guard open excavations and to allow for material curing times.
The civil works are due to be completed on Friday 24 October 2025.
From Monday 27 October to Thursday 30 October 2025 between the hours of 7am to 7pm daytime road closures will be in place, where we will begin our carriageway reconstruction works. This will include, utility survey works, the removal of the existing carriageway surface and replacing it with a new surface, along with the replacement of new road markings. Due to the size and scale of construction machines being used and to ensure the safety of the general public and workforce, it will be necessary to close the A515 Lichfield Road after the junction of Bradbury Lane to the junction of the A513 Alrewas Road.
When are the works taking place?
The works will start on Monday 20 October 2025 and all works are due to be completed by Thursday 30 October 2025.
How long will the works take?
It will take approximately 9 days to complete the works.
Will I be able to access my home/business?
Designated personnel will be positioned at either end of the road closure points to offer advice and assist with access to residential properties and business access within the closure points. Please speak to the site team, so that we can help with any specific needs or requirements you may have during this works.
A signed diversion route will be in place during the road closures.
Please plan ahead and allow extra time for your journeys.
Pedestrian access along the length of the works will be maintained throughout.
What effect could the works have on me?
We take care to make sure that work is completed with the minimum of disturbance to the local community but as with any major works, some minor traffic delays may occur.
The works may at times be noisy, and we apologise in advance for any inconvenience or disturbance caused. We’ll do our best to complete the work as quickly and safely as possible.
We would like to thank you for your patience during this works.
Please take care to plan your journeys and if necessary move vehicles to an accessible location.
Ahead of the works taking place, residential letters will be delivered to affected properties with specific scheme details
How you can help us
You can help us to get the job done with the minimum of fuss by following this advice:
- Please keep children away from the works to ensure their safety.
- Please drive slowly and cautiously through the works.
- Check your shoes before entering your property or car to make sure there is no bitumen from the works.
Further information
If you have any questions about the work or, concerns about how the work is being carried out, please do not hesitate to contact us via