Work is taking place on the A5192 Eastern Avenue in Lichfield to improve facilities for people walking and cycling near The Friary School.
The scheme is partly funded by the High Speed 2 (HS2) rail project and forms part of the Local Cycling and Walking Infrastructure Plan (LCWIP). These improvements will make it easier and safer for people to walk and cycle in the area.
The scheme includes:
A General Arrangement drawing showing an overview of the proposed highway works can be viewed below.
The main construction works are scheduled to begin on 20 July 2026, at the start of the school summer holidays. Carrying out the works during this period will help reduce traffic levels and minimise disruption to residents, businesses and road users.
Scheme completion is likely to be by the middle of September with all works substantially completed in front of the site entrance to The Friary School for the beginning of the Autumn Term.
The works will be carried out using temporary multi-way traffic signals.
Yes. The contractor will ensure that access to all homes and businesses is maintained throughout the duration of the works.
Some delays are likely while the works are taking place. Please allow extra time for your journey and plan ahead where possible.
To help the works progress safely and efficiently, please:
If you have any questions about the scheme or the construction works that are not covered in the FAQ, please contact:
Email: intraprojects@staffordshire.gov.uk
Or write to:
Staffordshire County Council
Staffordshire Place 1
Tipping Street
Stafford
ST16 2LP
This is a path that both pedestrians and cyclists can use.
There is usually no divider. You can recognise it by a blue sign showing a person and a bicycle.
A toucan crossing is a signal-controlled crossing that both cyclists and pedestrians can use at the same time.
You can find details about:
The project is funded through the County Council’s capital programme, with funding from HS2 Rail.
The works are expected to cost around £400,000.
No. The scheme is funded through HS2-related funding, not council tax.
The project will:
Yes. The scheme creates a safer, continuous route for cyclists.
It also improves links to the city centre and National Cycle Route 54, making cycling a more practical option.
Walking and cycling can:
The scheme links to wider health campaigns such as "Do It to Feel Better".
Walking and cycling help reduce emissions and improve air quality.
This scheme supports the County Council’s climate change plans.
The project has two main phases:
Yes, Eastern Avenue will stay open.
However, expect delays during busy times due to temporary traffic lights.
Yes. A new bus stop will be installed outside The Friary School.
The council will also coordinate with utility companies to reduce disruption.
Some noise is expected during working hours.
Bus operators have been informed. Any timetable changes will be shared by them.