CX030 Structural Maintenance Works on A513 Upper Gungate, Tamworth
Staffordshire County Council have now commenced works at A513 Upper Gungate and Aldergate, Tamworth on a £1,200,000 investment in the local area.
This scheme of work is due to take place between Lichfield Street and Comberford Road and also includes 160m section of Offa Drive. This work will be completed in 5 phases.
Work will include replacement of ironwork where necessary, repairing damaged drainage systems, replacing damaged kerbs and resurfacing the carriageway, traffic signal loops and road markings will all be replaced following surfacing.
Traffic management will vary dependent on which phase of works is live. Road closures will be required during civils and surfacing phases of the works. Details of the phases of works and expected dates of working are within the scheme letter and as tabled below.
When are the works taking place?
The work commenced on 10 February 2025 and will take approximately 12 weeks.
Timeline for carriageway works (Dates as a guide only and are subject to change)
Traffic Management | Work Type | Date properties affected | Section of road whereby properties may be affected by closures | Further comments |
Lane narrowing only |
Remove ironwork |
24.03.25 – 28.03.25 07:30-17:00 |
Phase 4. Railway Bridge to Croft St (Inc croft St junction). |
Lane narrowing only |
Road Closure and Diversion |
Civils, Plane, Binder and Surface Course |
24.03.25 – 01.04.25 19:30-05:00 |
Phase 4. Railway Bridge to 50m north of Croft St (Inc croft St junction). |
Working times 19:30-05:00. Exit permitted from College and Croft St to North only until 21:30. Restricted access during work times. Emergency access only to residents of Croft St during working times. |
Signals only |
Civils tasks |
24.03.25 – 01.04.25 09:00-17:00 |
Phase 5. North of Croft St to Comberford Rd (Fountain junction) |
When safe to work daytimes. Manually controlled signals during off peak times |
Road Closure and Diversion |
Civils, Plane, Binder and Surface Course |
29.03.25 – 03.04.25 09:30-23:59 |
Phase 5. North of Croft St to Comberford Rd (Fountain junction) |
Working times 09:30-23:59 Access to be made available to Landau Forte Academy entrance from Fountain junction only 14:45-16:30 |
Lane narrowing / temporary signals |
Jet and clear all drainage systems |
03.04.25 - 04.04.25 07:30 – 17:00 |
Phase 1- 5 All areas |
Mobile works, minor delays |
How long will the works take?
Approximately 12 weeks.
Will I be able to access my home/business?
For the safety of the public and of the work force, there will be phased traffic management including road closures. Where road closures are required a full diversion route will be in place.
Please help us to complete our works swiftly and safely by accessing at times when roads are open. Gatemen will be at road closure points if urgent access is required.
What effect could the works have on me?
We take care to make sure that work is completed with the minimum of disturbance to the local community but as with any major works, some traffic delays may occur.
Although we will do our best to ensure that noise pollution is kept to a minimum, it is likely that construction noise will be heard during the working times.
Please take care to plan your journeys as delays may be expected during the works.
How you can help us
You can help us to get the job done with the minimum of fuss by following this advice:
- Please keep children away from the works to ensure their safety.
- Please drive slowly and cautiously through the works.
- Check your shoes before entering your property or car to make sure there is no bitumen from the works.
Further information
CX030 Phases of work - letter to residents
CX030 A513 Upper Gungate & Aldergate - Scheme update letter 3 March 2025
CX030 A513 Upper Gungate & Aldergate - Scheme update letter 12 March 2025
CX030 A513 Upper Gungate & Aldergate - Scheme update letter 24 March 2025
If you have any questions or concerns, please do not hesitate to contact us via;
Enquiries: www.staffordshire.gov.uk/reportit