View our Permit Scheme Performance and Evaluation Reports.
Last updated: 29th July
Staffordshire County Council, in August 2019, received cabinet approval, in exercise of its powers conferred by section 33A (2) of the Traffic Management Act 2004 and all other enabling powers to commence operating a permit scheme on all publicly maintained roads within its authority boundary, as set out in the Schedule to the Order in terms commonly known as the “West and Shires Permit Scheme”. The objectives set out were:
The county council elected to join the already established “West and Shires Permit Scheme” which our neighbouring highway authorities were already part of including Shropshire, Telford & Wrekin, Cheshire East, Warwickshire, Coventry and Worcestershire. The benefits to this were to join an already established scheme and gain access to the expertise and knowledge of the highway authorities operating under this framework.
The permit scheme went live on the 1st April 2020, just over a week after the first national lockdown during the covid pandemic. Therefore the first two years of data in the reports were taken with caution as the highway network was operating differently during the pandemic and works, such as major renewal schemes were brought forward on major routes whilst disruption to the public would be at a minimum, compared with typical years. Prior to April 2020, the authority was notified of proposed works in the highway via Street Works notices.
The consultation on the introduction of the West and Shires Permit Scheme by Staffordshire County Council ran for a period of 12 weeks commencing on Wednesday 27 November 2019 with a deadline for receipt of responses no later than Friday 14 February 2020. An online survey completed the consultation process, open to those affected by the introduction of the scheme, as well as interested stakeholders and members of the public. At the foot of this page is a report which provides a summary of the responses received during the consultation on the implementation of the West and Shires Permit Scheme (WaSP) and other relevant documentation required for the authority to become a Permit Scheme Authority.
The third year of operation of the scheme has highlighted some significant positive outcomes that represent real benefits to the people and businesses of Staffordshire alike, for example:
Whilst the management of road and street works and other highways activities has continued to improve in terms of the overall objectives in year three of the operation of the WaSP scheme, it is recognised that there are improvements still to be made, such as:
The consultation on the introduction of the West and Shires Permit Scheme by Staffordshire County Council ran for a period of 12 weeks commencing on Wednesday 27 November 2019 with a deadline for receipt of responses no later than Friday 14 February 2020. An online survey completed the consultation process, open to those affected by the introduction of the scheme, as well as interested stakeholders and members of the public. The purpose of this report is to provide a summary of the responses received during the consultation on the implementation of the West and Shires Permit Scheme (WaSPS).