Structural maintenance

We are responsible for maintaining all public roads and footways in a safe and serviceable condition. Structural maintenance is the collective term for activities which maintain the integrity of the road and footway structures which make up the network. It comprises good value, planned maintenance activities such as footway and carriageway resurfacing/reconstruction. 

Reporting period

April 2026 to March 2027

Programme information is correct at the time of publication. Delivery dates and programme details may change because of weather, emergency works, utility works, funding or operational requirements.

Scheme status

Status Meaning
Complete Work has been completed
Ongoing Work is currently underway
Programmed Work is scheduled but has not yet started

Ongoing schemes

Road Location Work type Programme period Status
Leek Road (Cellarhead junction) Cellarhead Carriageway resurfacing 2 February to 17 November 2026 Ongoing
Lower Heamies Lane Eccleshall Carriageway resurfacing 15 June to 10 July 2026 Ongoing
Bower End Lane Madeley Carriageway resurfacing 17 August to 3 September 2026 Ongoing
Derby Road (Phase 3) Burton upon Trent Carriageway resurfacing 11 May to 14 August 2026 Ongoing

Programmed schemes

Road Location Work type Programme period Status
Delphouse Road Cheadle Carriageway resurfacing 29 June to 28 July 2026 Programmed
Newcastle Road (site investigation works only) Coates Heath and Mill Meece Site investigation works 20 July to 28 July 2026 Programmed
Newcastle Street and Radford Street Stone Carriageway resurfacing 13 July to 15 October 2026 Programmed
Lodge Lane Island Saredon Carriageway resurfacing 27 July to 18 August 2026 Programmed
Bretby Lane (including island) Burton upon Trent Carriageway resurfacing 3 August to 9 October 2026 Programmed
Pye Green Road crossroads Hednesford Carriageway resurfacing 31 August to 30 October 2026 Programmed
Gloucester Road and Newchapel Road Kidsgrove Carriageway resurfacing 5 October 2026 to 5 March 2027 Programmed
High Street Pattingham Carriageway resurfacing 19 October to 30 October 2026 Programmed
The Parkway Perton Carriageway resurfacing 19 October to 30 October 2026 Programmed
Wimblebury Road Hednesford Carriageway resurfacing 2 November to 13 November 2026 Programmed
Conway Road Knypersley Carriageway resurfacing 18 November 2026 to 27 April 2027 Programmed
North Street Newcastle-under-Lyme Carriageway resurfacing 15 February to 26 February 2027 Programmed
Wharf Road Biddulph Carriageway resurfacing 1 March to 12 March 2027 Programmed
Stafford Road and Wheelwright Drive Eccleshall Carriageway resurfacing 15 March to 26 March 2027 Programmed
Derby Road Uttoxeter Carriageway resurfacing Date to be confirmed Programmed

Completed schemes

Road Location Work type Completion status
Meadows Way Biddulph Carriageway resurfacing Complete
Latherford Lane Latherford Carriageway resurfacing Complete
Walsall Road Norton Canes Carriageway resurfacing Complete
Worthington Way Burton upon Trent Carriageway resurfacing Complete
Towns Meadow Way Uttoxeter Carriageway resurfacing Complete