Our use of cookies

We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work, please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 
Visit the Staffordshire County Council newsroom homepage
 

Branston Bridge works due to finish in July

Posted on Friday 23rd May 2025
Branston Bridge NEWSROOM

Work to reinforce Branston Bridge so it can open to traffic is due to finish in July.

Work is progressing well on site, but due to the number of unexpected services that have had to be diverted, replaced or worked around, the programme of works has had to be extended.

Engineers have worked with the various utility companies to ensure these works have been completed as soon as possible, but this has still influenced the length of time the bridge will be closed. 

Crews are now progressing well with the concrete saddle that will reinforce the bridge.

They have already moved to the south side of the road, planed off the surface, and excavated for part of the saddle with some concrete already poured.

After the concrete has reached the required strength, work will begin to install temporary supports for a live water main. This is so the remaining section can be excavated ready for more concrete to complete the saddle.

Once the final layer of concrete has been cast, drainage will be installed at each end, kerbing and paving will be laid, repointing of brickwork to the parapet will be completed, and the road will be resurfaced.

The completion date is currently scheduled for July 10, however this may change if other issues are found with the bridge or the utility pipes within it, or weather conditions turn unfavourable.

Monitoring equipment installed on the bridge has also recorded movement of the structure. This will continue to be monitored, and engineers are also liaising with Network Rail on this issue.

Staffordshire County Council’s Cabinet Member for Strategic Highways, Peter Mason, said:

“Crews have been working incredibly hard to reinforce the bridge and ensure it can be opened to traffic once more. While they are working hard to get the work done as quickly and as efficiently as possible, with work of this nature there is always the chance that it could be extended.

"When excavating for the works, and at the crown of the bridge, the crew are working with only a few courses of old bricks between them and the live railway below. It is important that they ensure they allow concrete to cure and strengthen fully as each stage of the works progress, and one reason why these works are perceived to be taking time to complete. We will not put pressure on crews to take unnecessary risks just for a speedy outcome.

“We are also having to work around a live water main which creates a considerable force as water flows through it and changes direction, and will need to be protected. There is always the risk that more unknown services could be found that will need diverting. Added to that, although the weather has been kind so far, this is another factor that could result in the work having to continue beyond 10 July. On the other hand, if we don’t encounter any more issues, work could finish ahead of schedule.

“Our crews are working as hard as possible, and we will continue to keep people updated on the progress we are making via the county council’s social media channels, and the East Staffordshire Highways Newsletter.”

People can sign up to the East Staffordshire Highways Newsletter here.

Related Items

Sorry, there are no related items