Our use of cookies

We use strictly necessary cookies to make our site work. These cookies enable core functionality such as security, network management, and accessibility. The cookies collect information in a way that does not directly identify anyone. For more information on how these cookies work please see our privacy policy.

To agree to our use of analytical cookies, click the 'Accept cookies' button. No, give me more information.
Accept cookies Reject analytical cookies Manage cookies
 

Why is the road closed/traffic management in place but no work is being completed?

Question:
Why is the road closed/traffic management in place but no work is being completed?
Answer:

When non-emergency works are undertaken on the highway a notice has to be made by the company which intends to carry out the activity. This notice will have a proposed start and end date and during this time there may be a presence of traffic management such as temporary traffic signals or lane closures, even if for a period of time no workforce is on site. The reason for this could be one of many and in all cases where residents have concerns about third-party works on the highway, we ask that contact is made with the company involved as they are ultimately responsible for the delivery of their own works and ensuring effective traffic control.

There are no results that match your search criteria