We use cookies on this site We and our partners use cookies and collect information from your browser. This lets us deliver content and relevant adverts to you. It also helps us to understand our audience better. See our privacy policy to learn more about how we manage your data and your rights. See our cookies policy to see how we use cookies and tracking technology. To agree to our use of cookies, click the 'Accept' button.
 
Advertisement

High speed rail proposals

''

As a county council, we remain focused on getting the best deal for Staffordshire in terms of mitigation, compensation for residents, economic benefits and improved connectivity.

We petitioned against Phase 1 and successfully achieved the lowering of 8 km of the line in Lichfield. We also secured an assurance that the Handsacre link, connecting HS2 to the West Coast Main Line, would be constructed. This will provide the infrastructure needed for Staffordshire to receive HS2 services and benefit economically.

On 17 July 2017, the Phase 2a hybrid Bill was deposited in Parliament. The Bill seeks powers to build the route from the West Midlands through Staffordshire to Crewe. The County Council petitioned this Bill in Parliament and achieved several improvements to the existing mitigation including an assurance to lower the line of route as it passes near Kings Bromley on viaduct, and a multi-million pound package of highways improvements.

The Department for Transport deposited its second additional provision (AP2) to the Bill on Friday 8 February 2019. Petitioning against AP2 runs from Friday 15 February to Friday 15 March 2019. The County Council is currently producing a detailed response to the consultation; it has not yet made a decision on petitioning AP2. AP2 documents can be found here.

The Phase 2a Hybrid Bill is at committee stage in the House of Commons, during which petitioners present their cases on the Bill and its additional provisions to Select Committee. Select Committee has published two reports to date. The Bill must pass through a further report stage and third reading before moving to the House of Lords. Royal Assent is expected to be given around the end of 2019.

Further Questions?

We have created a dedicated section which answers the most frequently asked questions.

Phase 1

What are the timescales for this phase?

The Phase One hybrid bill was submitted to parliament in November 2013. It has now completed the Parliamentary process in both houses and received Royal Assent in February 2017: this is when the Queen formally agrees to make the Bill an Act of Parliament. It granted deemed planning permission for the construction, operation and maintenance of HS2 Phase One.

The first part of construction, the enabling works (for example, archaeology, utilities diversions, early planting), has now commenced. Main civil engineering works are currently due to commence in 2019. The line is expected to open to passengers in 2026.

For more information please visit the HS2 website.

What will the new line do?

Link London to the West Midlands with a connection onto the West Coast Main Line at Handsacre in Lichfield. In Staffordshire, the railway will pass through Lichfield District and through the Parishes of Drayton Bassett, Hints, Weeford, Swinfen and Packington, Whittington, Fradley and Streethay, and Kings Bromley. The 12 mile railway through Lichfield joins the West Coast Main Line near to Handsacre.

‘Classic compatible’ high speed services will run from Stoke-on-Trent and Stafford, starting on the West Coast Main Line then joining the high speed line via the Handsacre link.

Find out about the environmental impact of the new line.

Can I petition against this phase?

No, petitioning on Phase One has now closed. Existing petitions against the bill are on the HS2 bill select committee website

As a result of our petition we received four assurances from HS2 Ltd. We will continue to work through the remaining items in our petition to reach the best possible outcome.

View the assurances and undertakings.

Can I claim compensation?

The residents’ charter and further information on the compensation schemes are available on the .gov website.

Phase 2

On 30 November 2015, then Chancellor, George Osborne confirmed the accelerated route from the West Midlands to Crewe, referred to as Phase 2a. It is expected that Phase 2a will open in 2027, six years ahead of the remainder of Phase 2. This is subject to its own Hybrid Bill, which was deposited in Parliament on 17 July 2017.

The Bill seeks powers to build the route from the West Midlands through Staffordshire to Crewe. As part of this, a full Environmental Statement (ES) was produced. This was subject to a ten week consultation, offering members of the public the opportunity to comment. This closed on 30 September 2017. Staffordshire County Council submitted a joint response with Lichfield District Council, Stafford Borough Council and Newcastle-under-Lyme Borough Council. 

The Bill received its Second Reading in the House of Commons on 30 January 2018. This triggered a petitioning period which ran until 26 February 2018. The County Council petitioned on a range of matters (some jointly alongside District and Borough Councils).

The Department for Transport deposited an additional provision (AP1) to the Bill on Friday 23 March 2018. Petitioning against AP1 closed on Friday 27 April 2018. The County Council submitted a response to the consultation but did not petition the additional provision. AP1 documents can be found here. 

The Department for Transport deposited a second additional provision (AP2) to the Bill on Friday 8 February 2019. Petitioning against AP2 runs from Friday 15 February to Friday 15 March 2019. The County Council is currently producing a detailed response to the consultation; it has not yet made a decision on petitioning AP2. AP2 documents can be found here.

The Bill is likely to receive Royal Assent towards the end of 2019.

Further information on the Bill’s progress through parliament can be found here

At this stage no construction routes have formally been approved by the County Council and any highway improvements proposed by HS2 Ltd. will need to be designed by HS2 Ltd. and approved by the County Council as stated in the Hybrid Bill.

Although the County Council has the right to object (on minimal grounds) to the use of construction traffic routes where there are more than 24 movements a day, if agreement cannot be reached with HS2 Ltd the matter will need to be referred to the SOS for Transport for a decision.

What will the new line do?

Introduce a new line north from Birmingham to Manchester and Leeds. It will provide 211 miles of new railway line and new stations linking the West Midlands, North West, East Midlands and Yorkshire.

View the route map for West Midlands to Leeds and Manchester

The consultation for this route took place between July 2013 and January 2014.

We prepared joint responses to the route consultation:

Can I petition against this phase?

Petitioning for the main Bill in the House of Commons closed on 26 February 2018. There will be a further opportunity to petition this phase when the Bill passes to the House of Lords.

Second Reading in the House of Commons took place on 30 January 2018. This triggered a petitioning period which ran until 26 February 2018. The County Council petitioned on a range of matters including PRoW. The petition document can be found here.

A shortlist of key items was taken forward to Select Committee. The Council appeared on the 23 April on its headline item, the Whitmore to Madeley tunnel extension. The decision of the Select Committee on this matter was that they would not wish to recommend a tunnel at this stage, although a number of petitioners are yet to appear on this matter. A copy of the Select Committee’s first report can be found here.

The Council was scheduled to appear on its remaining items on 8 May 2018. These included Highways matters such as routing construction traffic out of Lichfield City Centre, minimisation of use of Yarnfield Lane and Beaconside, a suite of measures on the Stone railhead/IMB-R and protection of veteran trees and hedgerows, among other items. Following robust negotiations with HS2 Ltd., supported by our parliamentary agent and QC, a suite of assurances and undertakings on key items have now been agreed. Consequently, the Council did not appear at Select Committee on 8 May. The Council has reserved its position in relation to the point on land use and timing at Rugeley Power Station.

Negotiating assurances in this way retains control in the hands of the Council as far as possible. Should the Council have elected to appear at Committee, it is quite possible that all the offers from HS2 Ltd. would have been withdrawn, or at the very least reduced in number.

  • The Department for Transport deposited an additional provision to the Bill on 23 March 2018. A copy of the additional provision can be found here, which carried its own petitioning period. Petitioning against the additional provision closed on 27 April 2018. The amendments in the AP were minor in nature, and the County Council therefore did not petition. 
  • The Department for Transport deposited a second additional provision (AP2) to the Bill on Friday 8 February 2019. Petitioning against AP2 runs from Friday 15 February to Friday 15 March 2019. The County Council is currently producing a detailed response to the consultation; it has not yet made a decision on petitioning AP2. AP2 documents can be found here.

Can I claim compensation?

The exceptional hardship scheme can help property owners who are affected by the proposals for the Phase Two line of route. The residents’ charter and further information on other compensation schemes are available on the .gov website.

View more about the exceptional hardship scheme on the .gov website.

A consultation on the exceptional hardship scheme was launched on 28 January 2013 and ended on 20 May 2013. We submitted a joint local response:

A further consultation was launched in November 2015, seeking the views of the public on the proposal to implement the same long-term property assistance schemes for this section as for Phase One. The County Council prepared a joint response with Lichfield District Council, Stafford Borough Council and Newcastle Borough Council, which can be viewed below.

HS2 Ltd.’s response summary report can be viewed here.

Phase 2a consultations

In September 2016, HS2 Ltd. issued a set of consultations relating to the Phase 2a line of route: from Fradley to Crewe. These were: 

  •  HS2 Phase 2a (West Midlands to Crewe) Working Draft Environmental Impact Assessment (EIA) Report consultation. This presented draft environmental information based on the current stage of design and assessment of Phase 2a. It included a description of the existing environment; an evaluation of the anticipated environmental impacts of the scheme; and the measures proposed to manage these impacts.

    The authority’s joint response can be viewed below:

  • HS2 Phase 2a (West Midlands to Crewe) Working Draft Equality Impact Assessment (EQIA) Report consultation. This presented draft equality information based on the current stage of design of the Proposed Scheme.
  • HS2 Phase 2a: West Midlands to Crewe Design Refinement consultation.  This covered three changes deemed significant enough to consult on separate to the main draft Environmental Impact Assessment (EIA); one of which is in Staffordshire. This is the construction of a temporary railhead near Stone, which potentially could be converted to a permanent maintenance facility.

The authority’s joint response can be viewed below:

HS2 community support fund

What is the fund?

Each County Councillor whose division is affected by the line of route of Phase 2a has been allocated a budget of £3,500 to support the communities affected by the route. County Councillors who are indirectly affected have been allocated a budget of £500 for the same purpose. Application criteria will mirror those for the Phase One fund, as follows:

Councillors can use the fund to:

  • Raise awareness. For example, producing information leaflets publicising HS2 consultations, mitigation, HS2 community newsletters and notification of public meetings/events.
  • Hire village halls/venues and the production of mitigation documents and plans.
  • Fund reasonable transport costs to support participation in the Phase 2a parliamentary process.

Councillors cannot use the fund to:

  • Hire experts or consultants.
  • Fund travel expenses without agreement by the Director of Strategy, Governance and Change.
  • Fund hotel expenses or subsistence costs.
  • Support or promote any national campaign.

Can I apply for less than the cost of my proposal?

Yes, but we can't pay a grant unless you've raised or secured the rest of the funds. If your County Councillor recommends funding which is less than you have asked for, they must know how you will raise or secure any shortfall between what they are recommending and the total amount needed for your proposal.

Apply for funding 

Before applying, please contact your local Councillor to talk about your request. They will see if your proposal could be put forward for consideration, and check that they have the funds required to support your application.

Please note: funding cannot be allocated as a lump sum payment. This means that an application will need to be submitted each time funding is required.
You can apply for funding by completing the form below and sending it to your local Councillor.

Who approves the funding?

The Director of Corporate Services normally approves a proposal by a Local Member to spend from his/her HS2 allocation unless: 

  • The proposal is one which is reserved to the County Council under Appendix 1 of this Constitution.
  • It is contrary to a County Council or Cabinet policy.
  • The Director of Director of Corporate Services advises it is unlawful.
  • It is a matter which would involve a payment or support to national HS2 campaign groups.
  • It would create an on-going financial commitment.
  • It relates to a function which is the legal responsibility of another statutory body or organisation.

What is needed for approval?

It is expected that applications for grant money will include supporting information showing expected costs, including estimates from third party organisations where relevant. On receipt of an application, the County Council reserves the right to request further evidence demonstrating that expenditure is in line with the terms and conditions of the scheme.

How is payment made? 

Payment of grants will be made via BACS transfer to an action group or Parish Council bank account. Transfer will not be made to individuals, except
in the case of travel expenses relating to Select Committee. Travel receipts
and evidence of appearance at committee must be provided. In any financial year, no proposal to spend an allocation of the fund will be approved after 31 January of that financial year. 

Can payments be granted for past actions?

After discussion and approval with the Local Member, payments can be made for past actions under the scheme. All applications for these payments must be submitted with proof of expenditure, e.g. receipts and invoices. Applications for retrospective payments must be received within three months from the date the money was spent.

Review 

The Director of Corporate Services may issue further guidance as necessary.

Further information

You can find further information can be found on the gov.uk website.

We also have a dedicated section which answers the most frequently asked questions.

There are no results that match your search criteria

Share this information
  • facebook17
  • twitter17
  • google17
  • intagram17
  • email17