Borough of Stafford
|
Type of Project
|
Status of Project
|
Estimated Works Costs
|
|
C0132 Hextall Lane, Ranton|
|
Hextall Brook Bridge Replacement
|
Completed March 2012
|
|
|
C0258 Salt Road, Salt|
|
Footway and carriageway resurfacing
|
Completed April 2012
|
£165,000
|
|
B5026 Main Road, Croxton|
|
Drainage, Kerbing and Carriageway Resurfacing Works
|
Completed April 2012
|
£202,000
|
|
U3031 Rickerscote Road, Stafford|
|
Footway Resurfacing
|
Under construction
|
£160,000
|
|
D2413 Beacon Rise, Stone
|
Footway Resurfacing
|
In programme for June 2012
|
£150,000
|
|
D2413 Tilling Drive, Stone
|
Carriageway Resurfacing
|
In programme for July 2012
|
£210,000
|
|
D2170 Outlon Road, Oulton
|
Footway Resurfacing
|
In programme for July 2012
|
£135,000
|
|
A34 Redhill Roundabout, Stafford
|
Carriageway Resurfacing
|
In programme for October 2012
|
|
|
C0002 Swynnerton Road, Eccleshall
|
Footway Resurfacing
|
In programme for November 2012
|
£100,000
|
|
C213 Clayalders Bank, Podmore
|
Carriageway Resurfacing
|
In programme for January 2013
|
£250,000
|
|
D4575 Crows Nest Lane, Coton End
|
Carriageway Resurfacing
|
In programme for 2012-2013
|
£17,000
|
|
D4587 Pooley Lane / Post Office Lane, Moreton
|
Carriageway Resurfacing
|
In programme for 2012-2013
|
£80,000
|
|
A5013 Creswell Grove, Stafford
|
Footway Resurfacing
|
Completed October 2011
|
£176,000
|
|
A0513 Weeping Cross / Milford Road and A0034 Cannock Road
|
Footway and Carriageway works
|
Completed October 2011
|
£596,000
|
|
D2412 Valley Road Estate
|
Footway Resurfacing
|
Completed November 2011
|
£90,000
|
|
U3031 Glebefields, Woodseaves
|
Footway and Carriageway Resurfacing
|
Completed October 2011
|
£46,000
|
|
A51 London Road, Pasturefields, Hixon
|
Carriageway Resurfacing
|
Completed January 2012
|
£300,000
|
|
D2384 Trent Close, Great Haywood
|
Footway and Carriageway Resurfacing
|
Completed December 2011
|
£30,000
|
|
Jordan Way / Holly Grove, Stone
|
Footway Resurfacing
|
Completed November 2011
|
£35,000
|
|
C0124 Green Road / A0518 Stafford Road, Weston Stafford
|
Bridge repairs
|
Completed July 2011
|
£75,000
|
|
C0087 Cold Meece to Norton Bridge Road, Yarnfield
|
Carriageway Resurfacing from approximately 600 metres south of Yarnfield Lane to Swynnerton Road
|
Completed July 2011
|
£500,000
|
|
A0518 Stafford Road, Aqualate
|
Widening of Coley Mill Bridge
|
Works to possibly start in the financial year 2011-12 due to the progress of a compulsory purchase order
|
£170,000
|
|
Walton High School, Phase 1
|
Traffic calming measures at Wildwood estate ring road
|
Partially complete, further consultation for an additional refuge being sought
|
£50,000
|
|
U3021 Ascot Road, Stafford
|
Footway Improvements
|
Completed June 2011
|
£95,000
|
|
A0520 Motorcycle Safety Routes
|
Casualty Reduction Project
|
Completed October 2011
|
Part of £1,051,000 over two years
|
|
Stafford Bus Interchange
|
Improvements to the bus interchange
|
Completed July 2011
|
£345,000
|
|
A518 Weston Road to University Route Strategy
|
Junction improvements at Weston Road Stafford District General Hospital entrance
|
Completed November 2011
|
£250,000
|
|
A34 Urban Route Strategy
|
|
Ongoing
|
|
|
Rising Brook Cycle Routes
|
|
Works planned for financial year 2011-2012.
|
£150,000
|
|
Stone Cycle Route A (Oulton Road / Cross Street / Longton Road / The Avenue / Mill Street)
|
|
Future scheme
|
£10,000
|
|
Stafford Western Access
|
|
|
£15,000
|
|
Rowley Park Stadium Car Parking Facilities|
|
|
Under negotiation.
|
£250,000
|
|
St Georges Hospital (Pritchard)
|
Section 278
|
Expected Spring 2012
|
|
|
Beacon Business Park
|
Section 278
|
Developer modifying drawings
|
|
|
Social Services (Foregate Street) SCC (Staffordshire County Council) -
|
Section 278
|
Hoardings have been erected.
|
|
|
Kingsmead North Walls Car Park & Retail
|
Section 278
|
Awaiting planning permission
|
|
|
Salt Works Lane
|
Section 111
|
Works to be delivered 2011-2012.
|
|
|
Mount Road, Stone
|
Section 111
|
Starting Christmas 2011
|
|
|
A51 Stone Road / D2087 Common Lane, Swynnerton
|
Section 111
|
Developer - future programme
|
|
|
Perkins Diesels
|
Section 111
|
Developer instructions awaited.
|
|
|
Tipping Street, Stafford
|
Section 111
|
Completed July 2011
|
|
|
Canalside Farmshop Great Haywood -
|
Section 111
|
Under construction
|
|
|
Castle View, Castletown
|
Section 111
|
Under construction - temporarily stopped
|
|
|
St Thomas Priory, Blackheath Lane
|
Section 106
|
Completed
|
|