District of South Staffordshire
|
Type of Project
|
Status of Project
|
Estimated Value of Project
|
|
C0026 Teddesley Road, Penkridge|
|
Carriageway Resurfacing
|
Under construction
|
£750,000
|
|
Featherstone Prison|
|
Associated highway works at New Road and Cannock Road junction for New Prison
|
Under construction
|
Funded by the Ministry of Justice
|
|
D4395 Boscomoor Lane, Penkridge
|
Major works to the Otherton Lane bridge / culvert
|
Completed December 2011
|
£35,000
|
|
D4192 Moatbrook Avenue, Codsall|
|
Footway Resurfacing
|
Completed March 2012
|
£105,000
|
|
B5012 Cannock Road, Penkridge
|
Carriageway Resurfacing
|
Completed February 2012
|
£86,000
|
|
C0217 Station Road, Codsall|
|
Footway and Carriageway Resurfacing
|
Under construction
|
£120,000
|
|
C0092 Pinfold Lane, Penkridge|
|
Repairs to Cuttlestone Bridge
|
Under construction
|
|
|
A0462 Bursnips Road / Essington Road junction, Essington|
|
Carriageway and Kerbing works
|
In programme to start early May 2012
|
£75,000
|
|
A0460 Cannock Road, Laney Green
|
Carriageway Resurfacing
|
In programme for 2012-13
|
£78,000
|
|
C0092 Stafford Street, Brewood
|
Carriageway and Footway Resurfacing
|
In programme for 2012-13
|
£47,000
|
|
D4471 Grange Road / Grange Avenue, Penkridge
|
Footway Resurfacing
|
In programme for 2012-13
|
£39,000
|
|
D4319 Filance Lane, Penkridge
|
Footway Resurfacing
|
In programme for 2012-13
|
£89,000
|
|
D4319 Wheatcroft Close, Penkridge
|
Footway Resurfacing
|
In programme for 2012-13
|
£6,000
|
|
D4451 Manor Avenue, Great Wyrley
|
Footway Resurfacing
|
In programme for 2012-13
|
£45,000
|
|
D4445 Kingswood Drive, Great Wyrley
|
Footway Resurfacing
|
In programme for 2012-13
|
£25,000
|
|
D4445 Pool View, Great Wyrley
|
Footway Resurfacing
|
In programme for 2012-13
|
£38,000
|
|
D4142 / D4159 Church Road / High Street, Wombourne
|
Footway Resurfacing
|
Completed February 2012
|
£330,000
|
|
D4270 The Warings, Wombourne
|
Footway Resurfacing
|
Completed January 2012
|
£15,000
|
|
D4416 Bratch Park, Wombourne
|
Footway Resurfacing
|
Completed January 2012
|
£62,000
|
|
Gains Lane near Great Wyrley
|
Bridge Replacement
|
Completed September 2011
|
|
|
D4108 Furnace Grange Road, Trescott Ford
|
Footbridge
refurbishment
|
Completed October 2011
|
|
|
Wombourne Parking Strategy|
|
Parking Strategy
|
|
|
|
B4156 Brownshore Lane / Wolverhampton Road, Essington from Bognop Road to High Hill
|
Resurfacing the full length of carriageway and repairing sections of damaged kerbs
|
Completed July 2011
|
£160,000
|
|
C0006 Birches Road, Codsall
|
Resurfacing the full length of carriageway
|
Completed July 2011
|
£45,000
|
|
A0460 Cannock, Shareshill
|
Carriageway Resurfacing
|
Completed June 2011
|
£477,696
|
|
D4371 Dundalk Lane, Cheslyn Hay
|
Carriageway Resurfacing
|
Completed June 2011
|
£98,000
|
|
D4496 Brookhouse Close, Featherstone
|
Footway Resurfacing
|
Completed July 2011
|
£27,000
|
|
D4244 Blythe Gardens, Codsall
|
Footway Resurfacing
|
Completed August 2011
|
£8,000
|
|
D4430 Park Road, Featherstone
|
Footway Resurfacing
|
Completed September 2011
|
£60,000
|
|
D4244 Chillington Drive, Codsall
|
Footway Resurfacing
|
Completed September 2011
|
£62,000
|
|
D4244 Roseville Gardens, Codsall
|
Footway Resurfacing
|
Completed October 2011
|
£10,000
|
|
D4244 Slade Gardens, Codsall
|
Footway Resurfacing
|
Completed October 2011
|
£4,000
|
|
D4244 Sherbourne Gardens, Codsall
|
Footway Resurfacing
|
Completed October 2011
|
£15,000
|
|
D4546 Cottage View, Codsall
|
Footway Resurfacing
|
Completed October 2011
|
£13,000
|
|
D4253 Poplars Drive, Codsall
|
Footway Resurfacing
|
Completed November 2011
|
£15,000
|
|
Wobaston Road junction Pendeford Mill
|
Section 278 Agreement
|
|
|